2025/0400(COD)E1st reading – European Parliament

Acceleration of permit-granting procedures

With the European Parliament, which is preparing its first-reading position.

Last active 15 Jun 2026

Track this billGet an email when the proposal moves: phase change, new document, or terminal outcome.

What this bill does

In plain terms: what it changes and who it affects.

The proposal speeds up permits for renewable energy, grids, storage, and recharging infrastructure across the EU.

Who it affects

It affects energy project developers, grid operators, storage providers, charging-station operators, local communities near projects, and users needing faster clean-energy infrastructure.

Core of the proposal
  • Creates single digital portals for renewable, storage, grid, and related permit procedures.
  • Sets shorter deadlines for storage, recharging stations, grid connections, and electricity grid infrastructure permits.
  • Expands overriding-public-interest presumptions for renewable projects and electricity grids until climate neutrality.
  • Requires benefit-sharing and independent facilitators for renewable projects above 10 MW.
Articles changed · 19 across 3 laws
  • Directive (EU) 2018/2001 (32018L2001)
    • art. 2: inserts new definitions in second paragraph
    • art. 15c: adds paragraph 6 on restricting large environmental exclusion areas
    • art. 15d: adds paragraphs 3 and 4 on benefit sharing and facilitators
    • art. 16: deletes digital-submission sentence and inserts single digital portal requirements
    • art. 16b: deletes species sentence and adds tacit approval rule
    • art. 16c: deletes paragraph 1 and adds repowering rules
    • art. 16d: replaces paragraphs 1 and 2; adds paragraphs 3 and 4
    • art. 16f: deletes final sentences and adds broader overriding public interest presumption
    • art. 16g: inserts rules on alternatives and compensatory measures
    • art. 16h: inserts permit-granting procedure for stand-alone energy storage
    • art. 16i: inserts permit-granting procedure for recharging stations
    • art. 16j: inserts permit-granting procedure for hybridisation of renewable energy plants
    • art. 17: replaces Article 17 on procedures for grid connection permits
  • Directive (EU) 2019/944 (32019L0944)
    • art. 8: replaces Article 8 on authorisation procedures
    • art. 8a: inserts rules on alternatives and compensatory measures
    • art. 40a: inserts network development and investment decision powers
    • art. 51: deletes Article 51
    • art. 59(1): inserts new point on approving network development plans
  • Directive (EU) 2024/1788 (32024L1788)
    • art. 8: amends authorisation procedures with resources, tacit approval and digital platform rules

Latest update

16 Jun 2026

The most recent development in this bill's progress.

1st reading – European Parliament → 1st reading – European Parliament

1st reading – European Parliament1st reading – European Parliament